Move events

How do I move events forward or backward?

Another way to change which dates events occur, in addition to Generate from dates, is to Move events.

Here you manually select how many days forward/backward selected event types should be moved.

1. Click on Events

Click on Events

2. Click on Adjust events

Click on Adjust events

3. Click on Select function and Move events

Click on Select function and Move events


Allow holidays


For your position, you may have chosen a day calculation method that controls events to be handled if they occur on holidays.

If you want the day calculation method to be ignored, check "Allow holidays".

If you ticked "Allow Holidays", you will be able to enter the first date on a holiday and subsequent events will also be able to fall on holidays.